EV Fleet Charging Peak-Demand & Transformer Sizer

Estimate EV fleet charging peak demand, an indicative transformer kVA and a user-entered monthly demand charge. The model compares charger simultaneity with the average power needed to deliver the fleet's daily energy within its charging window.

Result

Estimated transformer capacity

Estimated coincident site peak

Fleet energy per day

Average fleet charging power needed

Charging power at entered simultaneity

Minimum simultaneity for the energy window

Charging-window feasibility

Estimated monthly demand charge

How to use this tool

  1. Enter fleet size, daily kWh per EV and the hours available for charging.
  2. Enter charger nameplate kW and the simultaneous charging factor expected from your unmanaged or managed schedule.
  3. Add the existing coincident site peak, power factor, transformer design margin and utility demand charge if known.
  4. Check window feasibility, estimated peak kW, transformer kVA and monthly demand-charge estimate; compare these with an electrical site study.

Assumptions

Technical details: what the fields mean
EVs in fleet vehicleCount
Number of EVs served by this site or charging group.
Daily energy per EV dailyEnergyPerVehicleKwh
Average electrical energy that must be delivered to each EV per day, in kWh.
Charging window chargingWindowHours
Hours in which the fleet's daily energy must be delivered.
Charger nameplate power chargerPowerKw
Nameplate AC charging power per charger in kW; use the site configuration's applicable rating.
Simultaneous charging factor simultaneousChargingPercent
Share of the fleet's total charger nameplate power expected to be active at the same time. Managed charging can lower this value only if the energy-window check remains feasible.
Existing coincident site peak existingSitePeakKw
Existing site demand at the time the EV charging peak is assumed to occur; the model adds EV load coincidentally.
Power factor powerFactorPercent
Assumed site power factor as a percentage, used to convert kW to kVA.
Transformer design margin transformerDesignMarginPercent
Additional capacity margin applied after converting coincident kW to kVA. This is a planning input, not a code-mandated value.
Demand charge demandChargeGbpPerKwMonth
Utility demand charge in GBP per billed kW per month. The estimate assumes the modeled coincident site peak is the billable demand.
Methodology

Fleet daily energy = EV count × daily energy per EV. Average fleet charging power required = daily energy ÷ charging-window hours. Available charging power at the entered simultaneity = EV count × charger kW × simultaneity factor. The modeled fleet peak is the greater of available charging power and the average power required to meet the energy window; infeasible simultaneity is flagged. Site peak = existing coincident site peak + modeled fleet peak. Required transformer kVA = site peak kW ÷ power factor × (1 + design margin). Monthly demand charge = site peak kW × entered charge rate.

Worked example

30 EV fleet with an 8-hour overnight charging window

Inputs: EVs in fleet: 30 EVs, Daily energy per EV: 45 kWh/EV/day, Charging window: 8 hours, Charger nameplate power: 11 kW/charger, Simultaneous charging factor: 60%, Existing coincident site peak: 120 kW, Power factor: 95%, Transformer design margin: 20%, Demand charge: 25 GBP/kW/month

Result: The fleet needs 1,350 kWh/day and 168.8 kW average charging power. At 60% simultaneity, chargers provide 198 kW, so the window is feasible. Estimated site peak is 318 kW; with 95% power factor and 20% margin, transformer capacity is about 401.7 kVA. Estimated demand charge is £7,950/month.

Practical guidance
Common mistakes

FAQs

Why can the charging window be infeasible?

The entered simultaneous charger capacity may be lower than the average kW needed to deliver all EVs' daily energy within the available hours.

Does this choose a standard transformer size?

No. It estimates required kVA. Standard sizes, redundancy, harmonics, protection and local utility rules require an electrical design review.

Last reviewed: 2026-10-18

An early planning estimate for fleet charging load. It does not model charger taper, EV arrival/departure distributions, phase imbalance, harmonics, voltage drop, local grid studies, transformer standards or utility billing details.

This tool provides an indicative estimate, based on the assumptions stated above.